Bull Arm

bullarmmapBull Arm is one of the main construction sites for the Hebron Project. It is where project contractors Kiewit Kvaerner and WorleyParsons, along with numerous local subcontractors and suppliers will build the Gravity Based Structure (GBS) and living quarters and will assemble the Hebron platform.

 

Construction Timeline

Sept 2011: Began site preparation work which included road upgrades, refurbishing buildings and establishing site services. This work continued throughout most of 2012, including the installation of concrete batch plants and tower cranes.

Dec 2011: Received Comprehensive Study Report approval which enabled the construction of the bund wall for the dry dock area where the GBS will be built.

Oct 2012: Began the skirt installation, officially starting GBS construction.

2013: Begin topsides fabrication.

Construction and fabrication activities will proceed in parallel for several years. When the various topsides components are complete, they will all come together at Bull Arm for integration, hook-up and commissioning. The topsides and the GBS will then be mated, and the complete platform will be towed to the Hebron field.

Click here to learn more about the platform construction



infocentre

Bull Arm Information Centre

The Bull Arm Information Centre is open to the public and is a source of project information. The centre houses various information panels to allow visitors to learn more about the site, view photos of the work being done, and see what work we have planned for the future.

For additional information contact the Bull Arm Information Centre at:

 

Bull Arm Community Newsletter

 

 

Photo Gallery

Bull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm SiteBull Arm Site